NLNG Train 7 Project to Boost Nigeria Cooking Gas Capacity by 50%

Nigeria LNG Limited (NLNG) expects its ongoing Train 7 project to increase the nation’s cooking gas capacity by 50 percent upon completion. The 5 billion dollar expansion project is currently 90 percent complete, with pre-commissioning activities underway and an anticipated operational date in 2027. NLNG CEO Adeleye Falade confirmed that 16,000 workers are currently on-site, emphasizing the facility’s critical role in boosting domestic LPG supply and reducing reliance on imports.